Building Update!!!

Randy Wright, our Facilities Director, recently walked through the building site to provide us with a brief update on the construction progress to date. Please join us in thanking Randy for his time and the Lord for His amazing faithfulness to NWC.

South Wing:
· Classrooms are all painted and ceilings are being installed
· Gym equipment has been installed
· Gym is painted
· Kitchen is ready for paint
· Sound boards in gym, kitchen and music rooms are being installed

North Wing:
· Hanging of sheet rock, as well as mudding and taping is being completed
· Wiring for Heating/Ventilation/Air Conditioning is completed
· Framing is nearly finished

Mechanical Room:
· Finishing up

Roofing:
· Finished

Lobby:
· Windows are installed
· Sheet rock is done and mudding and taping is being finished

Misc:
· All windows have been installed
· Door frames are installed
· Doors will be installed last to prevent any damage