Building Update!!!
Randy Wright, our Facilities Director, recently walked through the building site to provide us with a brief update on the construction progress to date. Please join us in thanking Randy for his time and the Lord for His amazing faithfulness to NWC.
South Wing:
· Classrooms are all painted and ceilings are being installed
· Gym equipment has been installed
· Gym is painted
· Kitchen is ready for paint
· Sound boards in gym, kitchen and music rooms are being installed
North Wing:
· Hanging of sheet rock, as well as mudding and taping is being completed
· Wiring for Heating/Ventilation/Air Conditioning is completed
· Framing is nearly finished
Mechanical Room:
· Finishing up
Roofing:
· Finished
Lobby:
· Windows are installed
· Sheet rock is done and mudding and taping is being finished
Misc:
· All windows have been installed
· Door frames are installed
· Doors will be installed last to prevent any damage
South Wing:
· Classrooms are all painted and ceilings are being installed
· Gym equipment has been installed
· Gym is painted
· Kitchen is ready for paint
· Sound boards in gym, kitchen and music rooms are being installed
North Wing:
· Hanging of sheet rock, as well as mudding and taping is being completed
· Wiring for Heating/Ventilation/Air Conditioning is completed
· Framing is nearly finished
Mechanical Room:
· Finishing up
Roofing:
· Finished
Lobby:
· Windows are installed
· Sheet rock is done and mudding and taping is being finished
Misc:
· All windows have been installed
· Door frames are installed
· Doors will be installed last to prevent any damage
"Praise the LORD, all nations! Extol Him, all peoples! For great is His steadfast love toward us, and the faithfulness of the LORD endures forever. Praise the LORD!"
Psalm 117
Monday, November 21, 2011
Monday, October 24, 2011
Tuesday, October 4, 2011
Prayer Points
We are grateful to all of you who intercede on behalf of NWC and remind you that your consistent praying for us is no small act of service. Thank you!
Praise:
"Praise the LORD, all nations! Extol Him, all peoples! For great is His steadfast love toward us, and the faithfulness of the LORD endures forever. Praise the LORD!" Psalm 117
Praise:
- For the completed and continuing work on the elementary building...parking lot, landscaping, drywall, heating/ventilation, etc.
- For the beautiful weather we enjoyed in September.
- For the completion of the Firm Foundation Investment, LLC which is fully funded and was finalized on September 29th. Forty-three individuals invested a total of $7 million over the past 7 months which will allow the elementary building to be completed by March of 2012. Thank you Lord!!!
Prayer:
- Pray that the Lord would bless the investors of the Firm Foundation LLC and everyone who has donated time, prayer and/or finances toward the completion of the elementary building project.
- Pray that all aspects for completing the building (costs, construction, etc.) would go as planned.
- Pray that as we endeavor to elevate the Gospel at NWC, we would persevere through any opposition that takes place.
- Pray that we would increasingly become a community of praying people.
"...pray without ceasing, give thanks in all circumstances; for this is the will of God in Christ Jesus for you." 1 Thessalonians 5:17-18
Tuesday, September 13, 2011
Wednesday, August 31, 2011
Teacher Tour!!!
Last week our staff received a tour of the new Elementary Building. As you can see they are excited about moving in this spring.
Wednesday, August 24, 2011
Monday, August 22, 2011
Saturday, July 23, 2011
Monday, June 20, 2011
Tuesday, May 24, 2011
Preparing for Concrete!!!