Pages

Monday, November 28, 2011

Building Update!!!

Randy Wright, our Facilities Director, recently walked through the building site to provide us with a brief update on the construction progress to date. Please join us in thanking Randy for his time and the Lord for His amazing faithfulness to NWC.

South Wing:
· Classrooms are all painted and ceilings are being installed
· Gym equipment has been installed
· Gym is painted
· Kitchen is ready for paint
· Sound boards in gym, kitchen and music rooms are being installed

North Wing:
· Hanging of sheet rock, as well as mudding and taping is being completed
· Wiring for Heating/Ventilation/Air Conditioning is completed
· Framing is nearly finished

Mechanical Room:
· Finishing up

Roofing:
· Finished

Lobby:
· Windows are installed
· Sheet rock is done and mudding and taping is being finished

Misc:
· All windows have been installed
· Door frames are installed
· Doors will be installed last to prevent any damage


"Praise the LORD, all nations! Extol Him, all peoples! For great is His steadfast love toward us, and the faithfulness of the LORD
endures forever. Praise the LORD!"
Psalm 117

No comments:

Post a Comment